Skip to main content.

  • Attention

    Des traductions sont fournies pour aider les utilisateurs. Veuillez noter que toutes les données saisies dans le système doivent l'être uniquement en anglais.


    OK

    Attention

    Des traductions sont fournies pour aider les utilisateurs. Veuillez noter que toutes les données saisies dans le système doivent l'être uniquement en anglais.


    OK

Croatia: HEP GoGreen

General Procurement Notice

Project Name: HEP GoGreen
EBRD Project ID: 52803
Country: Croatia
Client Name: HEP - Hrvatska elektroprivreda
Type of Procurement: Goods,Works,Consultancy
Business Sector: Power and Energy
Notice Type: General Procurement Notice
Publication Date: 18/05/2022 14:34
Opportunity Status
This opportunity is for information purposes only
This opportunity is not yet open for response
This opportunity is now open for response
This opportunity is now closed for response
Access Opportunity
This opportunity is for information purposes only
This is a General Procurement Notice and cannot be responded to directly.

General Procurement Notice

1. Funding Details

The above named client intends to use part of the proceeds of a loan from/grant administered by the European Bank for Reconstruction and Development (the Bank) towards the cost of the above named project.

Additional financing information:
To be confirmed. A senior corporate loan of up to EUR 300 million to Hrvatska Elektroprivreda (the “Company” or the “HEP”), a joint stock company established in Croatia and 100% owned by the Government of Croatia (“GoC”)

2. Information on the Project

Project Description:
The project is currently under preparation and the final scope of the project will be defined soon, however, as part of the scope of the project, HEP intends to implement:
i. The construction of 5 solar power plants across Croatia with total capacity of nearly 130 MW (the “RES Sub-project”) and estimated investment cost of EUR 101,5 million.

ii. The implementation of more than 400k of advanced smart meters with 5k data concentrators (the “Smart Metering Sub-project”), 12k multifunction industrial meters in LV substations and construction of more than 21.5k control measuring points, with estimated investment cost of EUR 63,1 million.
iii. The modernization and extension of the electricity distribution infrastructure via in length of more than 10,650 km (“Distribution Sub-project”), with estimated investment cost of EUR 52,6 million, as well as distribution transformers with an estimated cost of EUR 33,3 million.

The remaining amount is potentially reserved for contingencies, given the complexity of the project, the start and duration of the construction, delivery time of goods as well as the current situation in Ukraine.


Estimated Total Project Value
300,000,000.00

Currency
EUR

Procurement Type
Goods,Works,Consultancy

Estimated Start Date of Procurement
18/05/2022.

3. Other Information

Contracts will be subject to the Bank's Procurement Policies and Rules and are open for participation for firms from any country, unless otherwise specified in the procurement documents.

Procurement under this project will be conducted using the EBRD Client E-Procurement Portal (ECEPP). If you intend to participate in any procurement under this project, please ensure that you have registered in ECEPP (https://ecepp.ebrd.com). Registered entities will be notified directly when any procurement opportunities are published.


4. Client Address
Ivan Palac
Hrvatska elektroprivreda d.d.
Strategy and development department
Ulica grada Vukovara 37
Zagreb
10000
Croatia
Tel. +38516322587
Email: ivan.palac@hep.hr