General Procurement Notice
1. Funding Details
The above named client intends to use part of the proceeds of a loan from/grant administered by the European Bank for Reconstruction and Development (the Bank) towards the cost of the above named project.
Additional financing information:
The Project costs, except for the Taxes as defined in the loan agreement, will be co-financed by the EBRD loan and the grant funds. The Project's goods, works and services will be either exempt from Taxes or such Taxes will be financed from the state budget.
2. Information on the Project
Project Description:
The Project requires procurement of the following goods, work and services:
- Construction of ca 220km double circuit 220kV overhead Choir-Sainshand transmission line and 220/110/35 kV substation at Sainshand and expansion of 220kV Choir substation;
- Project Implementation Support consultancy services;
- Supervision Engineer services
Estimated Total Project Value
77,000,000.00
Currency
USD
Procurement Type
Works,Consultancy
Estimated Start Date of Procurement
26/12/2022.
3. Other Information
Contracts will be subject to the Bank's Procurement Policies and Rules and are open for participation for firms from any country, unless otherwise specified in the procurement documents.
Procurement under this project will be conducted using the EBRD Client E-Procurement Portal (ECEPP). If you intend to participate in any procurement under this project, please ensure that you have registered in ECEPP (https://ecepp.ebrd.com). Registered entities will be notified directly when any procurement opportunities are published.
4. Client Address
Jargalsaikhan Burneebaatar
Ministry Of Energy Mongolia
Ministry of Energy Mongolia
Khan-Uul District, District 3, Genghis Avenue, Government Building XIV
Ulaanbaatar
17060
Mongolia
Tel. 976 88029698
Email: bjargalsaikhanmn@gmail.com