Bosnia And Herzegovina: GRCFW2 SARAJEVO PUBLIC BUILDINGS

General Procurement Notice

Project Name: GRCFW2 SARAJEVO PUBLIC BUILDINGS
EBRD Project ID: 51113
Country: Bosnia And Herzegovina
Client Name: Sarajevo Canton
Type of Procurement: Works,Consultancy
Business Sector: Municipal and Environmental Infrastructure
Notice Type: General Procurement Notice
Publication Date: 03/07/2023 09:29
Opportunity Status
This opportunity is for information purposes only
This opportunity is not yet open for response
This opportunity is now open for response
This opportunity is now closed for response
Access Opportunity
This opportunity is for information purposes only
This is a General Procurement Notice and cannot be responded to directly.

General Procurement Notice

1. Funding Details

The above named client intends to use part of the proceeds of a loan from/grant administered by the European Bank for Reconstruction and Development (the Bank) towards the cost of the above named project.

Additional financing information:
EUR 8 million EBRD Financing for Capex Costs
EUR 2 million REEP or SSF for Capex Costs
EUR 1.1 million Other Financing for TC Contracts
EUR 1.9 million Client funding for VAT expenses.

2. Information on the Project

Project Description:
The Project will finance the installation of EE measures in up to 40 buildings covered by the pre-feasibility study. The expected benefits include a reduction of energy consumption by at least 30 per cent or in absolute terms 14.4 GWh/year, which is equivalent to cost savings of EUR 1 million per year for the Canton’s budget. The Project is also expected to reduce CO2 emissions by around 5,000 tonnes per year. Additional benefits include a higher standard of heating and cooling and, thus, better comfort for the users of these public buildings.

Estimated Total Project Value
13,000,000.00

Currency
EUR

Procurement Type
Works,Consultancy

Estimated Start Date of Procurement
10/07/2023.

3. Other Information

The following contracts have been envisaged under the project:

- Consultancy Contract for Energy Audit and Detailed Design, including Technical specifications for Tender Documents;
- Consultancy Contract for PIU Implementation Support and Works Supervision for all the envisaged Works Contracts;
- Four (4) Works Contracts for reconstruction, rehabilitation or refurbishment of public buildings within Sarajevo Canton in accordance
with the conducted Energy audit results.



4. Client Address
Kenan Vehabovic
Project Implementation Unit - PIU
Sarajevo Canton
Reisa Džemaludina Čauševića 1
Sarajevo
71000
Bosnia And Herzegovina
Tel. +387(0)33 562-085
Email: mkipgo@mkipgo.ks.gov.ba