Albania: Technical supervision support during construction and commissioning of floating PV plant

Ebrd Contract Award Notice

Project Name: Floating photovoltaic power plant
EBRD Project ID: 51908
Country: Albania
Client Name: KESH - The Albanian Power Corporation
ECEPP ID: 14040156
Procurement Exercise Name: Technical supervision support during construction and commissioning of floating PV plant
Type of Procurement: Consultancy
Procurement Method: Consultancy Two Stage Open
Business Sector: Power and Energy
Notice Type: Ebrd Contract Award Notice
Publication Date: 07/08/2023 10:04
Opportunity Status
This opportunity is for information purposes only
This opportunity is not yet open for response
This opportunity is now open for response
This opportunity is now closed for response
Access Opportunity
This opportunity is for information purposes only
This is a Ebrd Contract Award Notice and cannot be responded to directly.

Ebrd Contract Award Notice

1. Contract Details


Contract Title: Technical supervision support during construction and commissioning of floating PV plant

Contract Description: Client intends to construct a Floating Solar Photovoltaic power plant on the reservoir of Vau I Dejes, where it already owns and operates one of Albania largest hydro power plants. The Lake of Vau i Dejes is located 20 km from Shkodra, 92 km from Tirana and 81 km from Tirana Airport.
The project includes design, supply and installation of the power plant with all related equipment, testing, commissioning, start-up and operation and maintenance of the plant for a period of at least two years.
The aim of this consultancy assignment is to provide a consulting services for technical supervision support during construction and commissioning of the floating PV plant. The project envisages technical support during the design and build period of 12 months and Operation Service Period of 24 months.

Contract Scheduled Completion Date: 16/10/2026

Date of Contract Signature: 18/05/2023

Signed Contract Value:
442,290.00 EUR

Lot(s):
No lots for this contract.


2. Contracting Party
RINA Consulting

Via Antonio Cecchi 6,
Genoa,
16129,
Italy


JVCA Partners:


Lead Partner: Yes
RINA Consulting S.p.a.
Via Antonio Cecchi 6,
Genoa,
16129,
Italy


Lead Partner: No
OCA Global Consulting and Technical Advisory Services S.L.U.
Via De las Dos Castillas 7,
Pozuelo de Alarcon, Madrid,
28224,
Spain


Lead Partner: No
Abkons Shpk
Rruga Themiostokli Germenji 6,
Tirana,
1001,
Albania




2. Contracting Party

RINA Consulting

Proposal Price (in evaluation currency): EUR 442,290.00
Proposal Price (Euro Equivalent): € 442,290.00

JVCA? Yes

JVCA Details:
Lead Partner Details:
RINA Consulting S.p.a.
Via Antonio Cecchi 6
Genoa, Italy, 16129

Other Partner Details:
OCA Global Consulting and Technical Advisory Services S.L.U.
Via De las Dos Castillas 7
Pozuelo de Alarcon, Madrid, Spain, 28224
Abkons Shpk
Rruga Themiostokli Germenji 6
Tirana, Albania, 1001

3. Other Information
No Other Information Provided

4. Client Address
Elida Bufi
KESH - The Albanian Power Corporation
Rr. “Viktor Eftimiu”, Nr. 12
Tiranë
1060
Albania
Tel. +355 4 2230888