Project Name: | Obigarm-Nurobod road project |
EBRD Project ID: | 49650 |
Country: | Tajikistan |
Client Name: | Republic of Tajikistan represented by the Ministry of Transport |
ECEPP ID: | 34575902 |
Procurement Exercise Name: | Regulatory Improvement support (RAMS) |
Type of Procurement: | Consultancy |
Procurement Method: | Direct Contracting |
Business Sector: | Transport |
Notice Type: | Ebrd Contract Award Notice |
Publication Date: | 16/05/2025 05:28 |
Opportunity Status | |
This opportunity is for information purposes only |
![]() |
This opportunity is not yet open for response |
![]() |
This opportunity is now open for response |
![]() |
This opportunity is now closed for response |
![]() |
Access Opportunity | |
This opportunity is for information purposes only | |
This is a Ebrd Contract Award Notice and cannot be responded to directly. |
1. Contract Details
Contract Title: Regulatory Improvement support (RAMS)
Contract Description: The proposed Obigarm - Nurobod Road Project aims to construct ca 75 km alternative alignment for the existing M41 highway connecting the northeast region of Tajikistan and the Kyrgyz Republic between Obigarm (72 km) and Nurobod (158 km).
The project road is divided into three sections: (1) the Obigarm - Tagikamar section is about 30 km long and includes 2 tunnels of 1.6 km and 1.7 km and local access roads of circa 30 km (Section 1); (ii) the Tagikamar-Nurobod is about 44 km long and includes 1 tunnel of 2.6 km, 1 long temporary bridge and local access roads of circa 40 km (Section 2); and (iii) section 3 includes a long permanent bridge that is about 760 m long and its approaches. These sections correspond to three contract packages that will be procured separately under the respectively ADB, EBRD and AIIB rules. Supervision consultancy services for each contract as well as Project Implementation support services are included in each respective package.
Contract Scheduled Completion Date: 09/11/2026
Date of Contract Signature: 08/04/2025
Signed Contract Value:
500,000.00 USD
Lot(s):
No lots for this contract.
2. Contracting Party
Corporate Solutions Consulting Ltd.