Project Name: | Suez Oil Processing Company Energy Efficiency and Upgrade Program |
EBRD Project ID: | 49454 |
Country: | Egypt |
Client Name: | Suez Oil Processing Company (SOPC) |
Type of Procurement: | Goods |
Business Sector: | Natural Resources |
Notice Type: | General Procurement Notice |
Publication Date: | 17/07/2019 10:38 |
Opportunity Status | |
This opportunity is for information purposes only | |
This opportunity is not yet open for response | |
This opportunity is now open for response | |
This opportunity is now closed for response | |
Access Opportunity | |
This opportunity is for information purposes only | |
This is a General Procurement Notice and cannot be responded to directly. |
The above named client intends to use part of the proceeds of a loan from, or Grant administered by, the European Bank for Reconstruction and Development ('the Bank') for the above named project. Additional financing details are as follows:
a loan from the European Bank for Reconstruction and Development (the Bank), Grant administered by the Bank
EBRD Loan Proceeds US$ 250,000,000 and in addition to US$ 12,000,000 from EU / NIP fund
The proposed project, which has a total estimated cost of 262,000,000.00 USD, will require the procurement of the following:
Tendering for the above contracts is expected to begin on 02/09/2019.
Contracts to be financed with the proceeds of a loan from/ grant administered by the Bank will be open to firms from any country.
The proceeds of the loan from, or Grant administered by, the Bank will not be used for the purpose of any payment to persons or entities, of for any import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations or under a law or official regulation of the Client's country.
Tendering for this project will be conducted by e-procurement using the EBRD Client E-Procurement Portal (ECEPP). Prospective participants who have registered in ECEPP and expressed an interest in the contract may access the documents and may request clarification and further information from the client through ECEPP. Non-registered firms should register on ECEPP in order to receive notifications via this link:
https://ecepp.ebrd.com/delta/viewNotice.html?displayNoticeId=8998955
Other Information:
The project has a total estimated cost up to about USD 260 Mln, and will require the procurement of the following goods, works and services:
1. Coker Refurbishment and Upgrade / new hydrotreating Unit – procurement in process
2. Supply and Installation of new Vapour Recovery Unit (VRU) – procurement in process
3. Energy Efficiency Investments – procurement to be initiated
4. VDU Asphalt Unit – procurement to be initiated (ECEPP - EBRD Client e-Procurement Portal)
5. Project Implementation Unit (PIU) Consulting Services – procurement completed
The procurement process for component 3 above is planned to be initiated during Q3 2019.
Client Address:
Eng. Hussein Awad
Suez Oil Processing Company (SOPC)
Suez City, Suez city, 100, Egypt